Portal de Jumilla

www.portaldejumilla.com

Jumilla - SpanishJumilla - English
detail of Jumilla

 

Underway the works of adaptation and functional improvement of the Plaza del Camionero (16/01/2019)

It will become a roundabout without traffic lights in order to decongest traffic in this area and gain security.

Inside it will be built an ornamental fountain 13 meters in diameter and the Truck Driver Monument will be placed on a pedestal

Last week the works of adaptation and functional improvement of the Plaza del Camionero Juan Soriano began, which will become a roundabout without traffic lights "with the aim of reducing traffic congestion in this area and gaining security as four avenues merge into it and a street, "said the mayor, Juana Guardiola.

"In these first days the works of demolition of the islets are being carried out with the aim of diverting the traffic so that the works are carried out with greater security", has indicated the Councilman of Works, Francisco González.

Also, both the mayor and the councilor of the area have ensured that the ceramic panel that has been damaged by chance will be replaced.

"All the elements that the area had will be maintained."

The roundabout will have two two-lane roads of 4 meters each, their corresponding sidewalks and a red micro-lane bike lane that will connect with Avenida de la Libertad.

New signage will also be installed, as well as new led lamps and will be relocated from existing ones as well as urban furniture.

The project includes the construction inside the central roundabout of a circular ornamental fountain of 13 meters in diameter, five water effects and submersible led lights of 10 colors.

In addition, a concrete base will be installed for the relocation of the Monument to the Trucker.

To solve possible floods, several mailbox-type scuppers will be installed at different points that will guarantee the entry of the runoff, being camouflaged under the sidewalk.

In addition, the rainwater collection system will be renewed.

The duration of the works will be about three months.

It will be carried out in five phases so that traffic can continue to circulate.

The works are being carried out by the company Construcciones Ruiz Alemán for an amount of 298,900 euros after a bidding process in which 12 companies were presented.

The duration of the same will be about three months.

Source: Ayuntamiento de Jumilla

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información