This week the renovation works of the Fueros street, between avenues of Levante and Reyes Católicos, began, which corresponds to the second phase of the work of the POS 2017 that also included the same section of Valencia Street, already completed. In Calle Fueros, the roadway, the sidewalks will be renewed, as well as a part of the potable water and sanitation network.
Its completion is scheduled for the end of May.
The works are being executed by the company Jumillana Riegos Ago with a cost of 95,729.40 euros, including Valencia Street, which was in the same project.
Both are included in the 2017 Works and Services Plan, which also included Avenida del Casón, whose renovation was completed last month and Goya Street, whose works began and consist of the completion of the road until it connects with Avenida de los Franceses through asphalted and new sidewalks.
The entire plan will cost 363,376.68 euros, of which 231,594 euros will be subsidized by the CARM and 131.782.68 will come from the City of Jumilla.