According to the notice, the works should be completed in a period of forty months, once proceed to the award of the contract, which could be done in the coming weeks
According to the deadlines set by the Ministry of Public Works in relation to the works of the A-33, today Wednesday, June 25, will proceed to the opening session of the tender dossier for the three batches that has divided the section between Jumilla and Yecla from the new highway.
As previously announced by the Ministry in January this year, the construction project was divided into three sections, in order to allow more opportunities would award work for companies, and it also could work simultaneously on all them, so that deadlines be shortened according to the notice in forty months.
This stretch of highway is an alternative to the old N-344, along which 5,500 vehicles daily, of which up to 23% are heavy.
Capture most of the traffic of long and medium haul and also will prevent the passage of vehicles cruises Romerales industrial estate in Jumilla, La Fuente del Pino and AlquerÃa.
The three construction contracts define a dual carriageway redrawing 23.4 km between Jumilla and Yecla.
In order to save the landforms as the Rambla de Jumilla, and enable continuity of existing linear works, ensuring the permeability of the highway, one viaduct, 14 overpasses and underpasses will be built in August.
Besides cross drainage works on watercourses intersected by the highway will be arranged.
With a budget of 97 million euros, representing a step to complete this highway that connects Murcia to Valencia inside.