Approved the initiation of project files del Castillo, industrial buildings, the road to Santa Ana Botanic Garden (09/02/2009)

The Government team spokesman Jesus Sanchez has reported on the most important agreements of the Bureau of Procurement and the Local Board concluded this morning.

Thus, the Committee shall have approved the start of record of the road projects and setting of the Castle, of the civil works for industrial buildings, expansion of the Botanic Gardens and the conditioning of the Santa Ana Road the procedure for awarding these projects to companies establishing a criterion, which awarded up to 55 points, depending on labor to hire.

Regarding the first, with a budget of 1,230,000 euros, has a running time of 7 months, will be the open, urgent calls for a rating to companies that attend and that it says Jesus Sanchez "are projects scale and with a large budget, so it must be solvent companies, both technically and financially. "

It has also approved the opening of the tender dossier for the civil works project of industrial buildings.

Promoting business development.

Through this work is going to build 4 industrial buildings on plot 35 of Polygon The Romerales Jumillano, two with an area of 500 square meters and two of 700 square meters.

In this case the execution time is 3 months and has a budget of 713,000 euros.

Another point addressed in the Bureau was the beginning of the file extension of the Botanic Garden.

Sanchez said "that will extend an extension of 15,600 square meters, taking advantage of a pine forest in the south of the garden, from the border with the Rambla, the road and the pump.

Going to redesign this public space, with the construction of leisure spaces, corridors with flagstone walkway, playground and is going to fix the front of the garden, with a parapet of lattice work and a forge.

In total green area will be an extension of 34,900 square meters, has a lead time of 8 months and a budget of 163,000 euros.

In addition, on urgent issues, has given approval to start the project file with the greater amount: the conditioning of the Carretera de Santa Ana, with a budget of 1,553,000 euros.

It will proceed to the preparation of this road and lighting, from the chapel of St. Augustine to Roalico area.

These works must be completed in seven months and is the open, as a matter of urgency and also requested, by the requirements of the law, a classification given to businesses.

Have been established and award criteria to rate companies that attend the following: It will be awarded 10 points for increased security for the execution of the work, 5 points for improvement of materials, 30 points for increasing or improving the units of the planned or budgeted items and, most importantly, 55 points based on labor to hire.

All these projects are funded 100% by the Central Government and the other projects, their records will be approved next week.

On the other hand, the Local Government Board has approved the initiation of disciplinary proceedings on the proposal of Councillor for Citizen Security, infringement, pursuant to the Organic Law 1 / 92 and for various reasons such as distortion of Public Safety, disorders in public, excessive hours and noise, causing inconvenience to residents and disrespect for authority.

It has given its approval to a registration request to the beneficiary of rural electrification work of the farm, "the electrification affecting 14 recipients and now are 15, the new beneficiary will be borne by expenditure and the proportion that are, "Sanchez said.

Finally approved a settlement of obligations amounting to EUR 123,697 for payment to suppliers providing services and products for maintenance and operation of services and municipal buildings, relating to electricity, printing, street cleaning and gardens, refuse and service theater, among others.

Source: Ayuntamiento de Jumilla

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información